Patil Builders and Contractors · PlinthBook

Find
Working date
6 Apr
Received basis
6 Apr · 19:00

Firm recorded cost ₹19,250 supported · gang cost basis missing

New wage dues ₹2,050 · Provisional supplier dues ₹14,000 · Collectible due ₹5,00,900 · Sharma Bill 3

Sharma residence

Cost ₹19,250 · Brickwork 85 sqm · 85/600 sqm · 14.17% in 6 days · projected 13 May · 38 days behind plan

Gokhale clinic

Nothing received today. No zero-cost or completed-day claim.

Some figures have a provisional or missing basis. Review the marked sources before treating them as a complete position.

No daily facts or no-work mark were received for this site's working day. This does not prove that no work happened.

No daily facts have been received for Patil Constructions · Gokhale clinic on 6 Apr. Work may still be on phones.

Sharma residence · dated dayReceived progressCost position
Site positionChange summary hourLater correction