- Working date
- 6 Apr
- Received basis
- 6 Apr · 19:00
Firm recorded cost ₹19,250 supported · gang cost basis missing
New wage dues ₹2,050 · Provisional supplier dues ₹14,000 · Collectible due ₹5,00,900 · Sharma Bill 3
Sharma residence
Cost ₹19,250 · Brickwork 85 sqm · 85/600 sqm · 14.17% in 6 days · projected 13 May · 38 days behind plan
Gokhale clinic
Nothing received today. No zero-cost or completed-day claim.
Some figures have a provisional or missing basis. Review the marked sources before treating them as a complete position.
No daily facts or no-work mark were received for this site's working day. This does not prove that no work happened.
No daily facts have been received for Patil Constructions · Gokhale clinic on 6 Apr. Work may still be on phones.
Sharma residence · dated dayReceived progressCost position