- Site
- Patil Constructions · Sharma residence
- As at
- 6 Apr
Brickwork, ground floor
85 / 600 sqm · 14.17% done in 6 calendar days from actual start 1 Apr
2.36% per day · 37 remaining days · projected finish 13 May
Master finish 5 Apr · 38 days slip
Brickwork stage
Expected billing 17 Jun · master 10 May
Waiting · first-floor work follows ground-floor finish; no bill issued
| Task | Master finish | Received progress | Projected finish | Movement |
|---|---|---|---|---|
Footings and plinth | 31 Jan | 62 of 62 cum · Complete | Actual 31 Jan | — |
Ground floor slab | 28 Feb | 180 of 180 sqm · Complete | Actual 28 Feb | — |
Brickwork, ground floor | 5 Apr | 85 of 600 sqm · In progress | 13 May | 38 days · measured pace |
Brickwork, first floor | 10 May | 0 of 540 sqm · Not started | 17 Jun | 38 days · starts 14 May after ground floor · 35-day duration |
Stage schedule
Daily progress
Owner summary
Revise schedule
Received quantity beyond BOQ
No positive progress is recorded, so there is no measured pace. The projection carries this task's current duration.
Brickwork, ground floor carries this task's projected start to 14 May.
Actual progress uses records received by the firm. Work still on phones may change this comparison when received.
Linked billing dates may move on this task's recorded basis. This does not issue a bill or demand, or promise receipt.
The Gantt plot is not printed. The task table gives dates and dependencies.
Space for proposed dates and questions