- Running bill 1 gross
- ₹2,82,000
- Advance given
- ₹50,000
- Recovered
- ₹50,000
- Remaining advance
- ₹0
- Retention held
- ₹14,100
- Tax assessment
- Unresolved · CA review
- Payable before unresolved TDS
- ₹2,11,900
- Paid
- ₹0
- Due date
- Unknown
Download a copy to keep. If this link closes, ask the sender for another.
Firm's measured basis · Brickwork 38 cum · Plaster 300 sq m
Bhaskar's response · 40 cum claimed · 38 cum agreed · 2 cum excess disputed · Plaster agreed
The firm's supported 38 cum is raised. The claimed 2 cum excess is not payable. The response and its evidence remain beside the bill.
- Issued-material recovery
- 20 bags issued · 5 returned · 15 net × ₹400 = ₹6,000 · WO-001
Tell Patil Constructions if the bill, recovery or retention differs from your account.