Party statement Bhaskar More Patil Constructions · Sharma residence As at Running bill 1 issue
- Gross
- ₹2,82,000
- Advance
- ₹50,000 given and recovered
- Payable
- ₹2,11,900 before unresolved TDS
- Paid
- ₹0
- Retention
- ₹14,100 held
- Measurement
- 38 cum brickwork · 300 sq m plaster · Version 1
- Response
- Measurement agreed · Settlement awaiting response
Signatory: Mahesh Patil
- Issued material recovery
- Cement · 20 issued − 5 returned = 15 bags × ₹400 = ₹6,000
- Issued-material recovery
- 20 bags issued · 5 returned · 15 net × ₹400 = ₹6,000 · WO-001