- Working date
- 6 Apr
- Received basis
- 6 Apr · 19:00
Firm total · New wage dues ₹2,050 · Provisional supplier dues ₹14,000 · Collectible due ₹5,00,900 · Sharma Bill 3
Sharma residence · Cost ₹19,250 · Wage dues ₹2,050 · Supplier dues ₹14,000 · Brickwork 85/600 sqm · 14.17% in 6 days · projected 13 May · 38 days behind plan
Gokhale clinic · Nothing received today · Not included as zero work or zero cost
Received basis at 7 pm includes 85 sqm progress. Unreceived phone work is not included.
Holidays and received “no work today” marks are not listed as missing reports; other received facts still count.
Recorded cost today · ₹19,250 · gang cost basis missing